Consisted of general projects throughout hospital to include consultation & construction documents as needed. The following are some of the projects completed at Forrest General.
- Surgery Renovation - Renovation of existing OR room to new heart OR, renovate existing nurses lounge to new General OR, renovate existing storage room to new nurses lounge for MEP and add new A. H.U. ductwork, filters, piping, plumbing, medical gases, and electrical design.
- Emergency Department Renovation - Renovation and addition to existing ER department consisted of 34,250 square feet. Included new medical gases with relocated medical tanks, towers, and gas piping.
- Lowery Woodall, Outpatient Surgery - Added two operating rooms, modified existing waiting room, and enclosed entry.
- Chest Pain Center - Renovation of existing emergency waiting area and medwell waiting and office areas for new chest pain center.
- Laundry Tunnel Washer - MEP connection to new laundry equipment for tunnel washer, dryers & existing relocated equipment. New steam, water, air & sewer piping. Ran new exhaust, air intake, and ductwork to new dryers.
- Boiler Room Area - Design development drawings for new 8,000-ton central plant and service tunnel for hospital facilities consisting of campus complex.
- Central Plant - Design development drawings for new 8,000-ton central plant and service tunnel for hospital facilities consisting of campus complex.
- Heart Catheter Area - 3,500 square foot renovation.
- Forrest General Hospital Dialysis Unit - Renovation of 4,000 square feet on 3rd floor.
- Forrest General Hospital Dietary & Chiller Plant
- Cancer Center Forrest General - Design development drawings for new 20,000 square foot cancer center.